demolition timeline

March 2017

Site office established on Greek Street

June 2017

Works to retain façade at 12/13 Greek Street begin

May 2018

Excavation works begin and will continue until November 2018

2017

2018

May 2017

Structural demolition works start on site from West (Wedgewood Mews/Greek Street) to East (Manette Street/Charing Cross Road)

Oct 2017

Piling works commence to form basement substructure prior to excavation

November 2018

Removal of equipment and clearance of site for construction